Roughly 1,400 linear feet of galvanized guardrail and grab rail, fabricated in-house from raw 20-foot stock.
The railing had to be built around the concrete as it was poured, and in the field concrete rarely lands exactly to plan. We fabricated to real conditions and kept pace with the pour so the project stayed on schedule.
Shop drawings, produced through our detailing partners and approved by the engineer of record, and full in-house fabrication.